Phase II Shrine Restoration Continues

Despite the coming of winter weather, work continues unabated in the Shrine restoration project! 
 
2022 01 phaseIIshrinerestoration1
 
 
Due to supply chain delays, the necessary PEX tubing for the future radiant heating has yet to arrive. Nevertheless, other work has been done: notably the placing of a moisture barrier over the gravel base in the nave, and the installation of the necessary interior and exterior plumbing for future bathrooms and sinks.
 
2022 01 phaseIIshrinerestoration2
 
 
Part 1 of Phase II will provide a 6” thick, structural concrete slab to the church’s narthex, nave, sanctuary, and basement as a foundation for the subsequent steps in Phase II.  
 
2022 01 phaseIIshrinerestoration3
 
Thank you for your generous support in these difficult times for the Church as you help build a stable home for the Institute in the United States, making visible the reign of Christ the King in all things!
 
2022 01 phaseIIshrinerestoration4
 
Conceptual rendering of the U.S. Provincial Shrine of Christ the King interior 
 
The total cost of this first part of Phase II is $765,000.
Would you like to invest in this important project to help ensure the stability and growth of the Institute in the United States of America?  We need your help!
 
 
With your generous help, we hope to complete Part 1 of Phase II by January 2022 and continue with Part 2 before year’s end.
 
You are helping to build a true throne for Jesus Christ our King in the heart of America.  May He, whom you honor with your offering in faith, bless you abundantly and protect you in these turbulent times!  Together, let us put Christ's house first.  
 
 