June Updates at Sacred Heart Retreat Center

2025 04 retreatcenter
 
Soon we will be closing our 8th month of construction. Work continues to progress on all floors, and the new electrical service is almost complete.

Key Construction Updates:

1st floor 1930’s wing.
* East Refectory is complete less finished wood trims and the new HVAC units being installed.
* West is complete less the new HVAC units being installed.

1st floor 1950’s wing.
* Painted. The new MEP finishes and units will be going in above the acoustical ceiling grid.

2nd floor 1930’s wing.
* East currently has the MEP finishes units going in above the acoustical ceiling grid.
* West work is complete less than the new HVAC units being installed.

2nd floor 1950’s wing. 
* The new MEP finishes and units being installed above the acoustical ceiling grid.

3rd floor 1930’s wing. 
* East is almost ready for above acoustical ceiling grid inspection with bathroom accessories and doors to follow.
* West Dignitary Suites is almost ready for above acoustical ceiling grid inspection with bathroom accessories and doors to follow.

3rd floor 1950s wing. 
* Is almost ready for above acoustical ceiling grid inspection with bathroom accessories and doors to follow.

WE Energies will be installing the new electrical service 6/27 and the mechanical contractor is starting to install the cooled water lines from the chiller into the building.

We look forward to updating the continued progress.
 
2025 07 juneretreatcenterupdates

See the latest construction update video HERE!